CONTACT

Sector:

STOR Power Generation

Location

Plymouth

Date completed:

2020
Blue Dots

Langage STOR

Our works involved the civil & structural design and build of all of the foundations for the site including construction of an access road, fencing, ducting, drainage and footpaths.

This was a greenfield site which was situated on a man made embankment which we had to carry out detailed geotechnical design on to ensure that the ground could take the loading from the generation plant

A number of existing services and easements were present across the site which we proved using ground penetrating radar and trial pitting to establish a safe system of work and to enable construction of the site in accordance with the requirements of the end customer.

 

Another successful project designed & delivered in partnership with EPS Construction. All arisings were reused on site and 100% of our waste was recycled.
Blue Back IconBack to Case Studies

7.5MW Gas Peaking Plant

Full Civils Design & Build

Civils & structural design and build

Would you like more information?

If you need any assistance with site clearance, earthworks, ground improvement, foundations, ducting, drainage, process pipework, kerbing, slabbing or fencing for your project or if you would simply like to find out more about the sort of work we do then please contact us.

GET IN TOUCH